Maintenance Schedule — KDW-230 (deck water seal); KSC-240 (scrubber); RX-415 (portable HC/O2 detector)

^Z S E M M

← Back to ^CIAK — KDW-230 (deck water seal); KSC-240 (scrubber); RX-415 (portable HC/O2 detector)

Maintenance Schedule

JobIntervalTypeSource
DP transmitters, recorder and panel indicators - zero/span adjustment, alarm settings 1 years calibrate Maker
Deck water seal - check water supply and level while plant is shut down 1 days check Maker
Deck water seal - yearly: wash demister pad, check lining and fitted components 1 years inspect Maker
O2 analyzer - calibrate and confirm proper operation 2 months calibrate Maker
O2 analyzer - check sampling piping and valves 3 months check Maker
O2 analyzer - clean sample filter, drain pot and drain filter element 1 months clean Maker
O2 analyzer - replace sample-filter cartridge and O-rings 1 years replace Maker
P/V breaker - clean flame screen 30 months clean Maker
Remote valves glands, pressure switches - half-yearly check 6 months check Maker
Remote/automatic valves, pneumatic DP transmitter, air header - weekly drains and valve operation 1 weeks check Maker
Scrubber - overhaul level switch 6 months overhaul Maker
Scrubber - yearly internal inspection (lining, packing, spray nozzles/headers, bolts) 1 years inspect Maker
Valve positioners, pneumatic transmitter supply air, machine-side indicators - monthly check 1 months check Maker