Maintenance Schedule — JMC-BIO AEROB-30N

^Z S E M M

← Back to ^RFJJ — JMC-BIO AEROB-30N

Maintenance Schedule

JobIntervalTypeSource
Aeration tanks #1/#2 - check sludge amount, colour and aeration sound 1 months check Maker
Aeration tanks - discharge sludge 4 months clean Maker
Air blower - clean suction filter with compressed air 1 months clean Maker
Discharge pump - lifting (shut-off head) test 1.4-1.6 kg/cm2 1 months test Maker
Ozone panel - check oxygen generator intake air filter 1 months check Maker
Ozone panel - replace oxygen generator intake air filter 1 years replace Maker
Sewage plant - daily checks (switches, air blower, sludge return sight glass, discharge pump) 1 days check Maker
Sewage plant - settle test of discharge water (250 ml / 30 min) 1 weeks test Maker
Sewage plant - wash sludge screen 1 weeks clean Maker