Maintenance Schedule

JobIntervalTypeSource
Auxiliary pump pilot pressure - check 1 weeks check Maker
Bolts, nuts, keys, knock-pins - check tightness 3 months check Maker
Chain couplings - first grease renewal 1,000 h initial Maker
Chain couplings - renew grease 2,000 h lubricate Maker
Filter - disassemble and check, renew element if dirty 1 years inspect Maker
Grease points (ram pin bush, tiller sliding surfaces) - grease 1 days lubricate Maker
Guide bar bearing bush - check clearance 3 months check Maker
Hydraulic pumps and auxiliary pumps - overhaul inspection 4 years overhaul Maker
Hydraulic system - check for abnormal noise/vibration, purge air 1 weeks check Maker
Hydraulic system - check oil leakage (ram packings, piping, valve blocks) 1 days check Maker
Line filter - renew 20-micron paper elements 6 months replace Maker
Oil supply tank - check oil level and temperature 1 days check Maker
Oil supply tank - inspect inside, clean and change oil if sludged 1 years inspect Maker
Oil tank level switch - overhaul and function check 1 years test Maker
Pump filter indicator - check 1 days check Maker
Ram pin bush - measure clearance 6 months inspect Maker
Ram pin, tiller and ram pin bush - inspect sliding surfaces 1 years inspect Maker
Rams, tiller, guide bar sliding surfaces - apply oil for rust prevention 1 weeks lubricate Maker
Steering gear and hydraulic pumps - appearance inspection 1 years inspect Maker
Working oil - examine property (colour, deposits, water) 6 months analyse Maker